Concrete Footing Calculator: Bags per Linear Foot

A footing is a long, shallow trench of concrete, so the count that matters is per linear foot. The standard residential strip footing is 16 inches wide × 8 inches deep. Here is what it takes.

0.89 ft³ Per linear foot (16 in × 8 in)
15 80 lb bags per 10 ft (exact)
3.29 yd³ Per 100 ft of 16 in × 8 in footing

Buy 17 × 80 lb bags per 10 ft to include the standard 10% waste allowance for trench walls that are not perfectly straight and soil that gives a little. Trench footings almost always run over the neat math, because the excavated trench is never exactly the drawn size.

Bags to buy per 10 ft of 16 in × 8 in footing (with 10% waste)

1780 lb bags
2260 lb bags
3340 lb bags

Footing Bag Table: Bags per 10 Linear Feet, by Footing Size

Exact counts are the mathematical minimum, rounded up. The "with waste" counts multiply the volume by 1.10 before dividing, which is the number to actually buy. Yields: 80 lb bag = 0.60 ft³, 60 lb = 0.45 ft³, 40 lb = 0.30 ft³.

Footing (width × depth)Volume per 10 ft80 lb exact80 lb +10%60 lb exact60 lb +10%40 lb exact40 lb +10%
12 in × 6 in5.00 ft³91012131719
16 in × 8 in8.89 ft³151720223033
20 in × 10 in13.89 ft³242631344751
24 in × 12 in20.00 ft³343745496774

To scale the table: find your footing size, take the per-10-ft count, and multiply by your total trench length divided by 10. A 60 ft run of 16 in × 8 in footing at the with-waste count is 17 × 6 = 102 bags of 80 lb mix. Odd trench lengths are exactly what the main calculator is for — enter the trench as a slab with the footing's width as one side and the total length as the other.

How Footing Sizes Are Chosen

A footing spreads the load of the wall above it over enough soil that the structure does not settle. Two dimensions do the work, and both are set by your situation, not by preference:

  1. Width depends on the load and the bearing capacity of your soil. Wider footings spread the same load over more ground. The 16 in × 8 in size in the quick answer is the common starting point for a one-story wall on average soil.
  2. Depth has two parts: the thickness of the concrete itself, and how far down the trench goes. The bottom of the footing must sit below the local frost line, so the trench depth in cold climates is mostly about frost, not strength.
  3. Local code sets the minimums. Frost depth, minimum width, and reinforcement requirements vary by jurisdiction and by what the footing carries. The sizes in the table are common examples for estimating concrete — confirm your required size with your local building department or a licensed professional before you dig.

Volume (ft³) = (W ÷ 12) × (D ÷ 12) × length in feet  ·  Bags = ft³ ÷ yield, rounded up

Worked example: a 16 in × 8 in footing runs (16 ÷ 12) × (8 ÷ 12) = 0.89 ft³ per linear foot. Over 10 ft that is 8.89 ft³, and 8.89 ÷ 0.60 = 14.8, so 15 bags of 80 lb mix exact — or 17 with the 10% cushion.

Worked Example: Footings for a 20 × 30 ft Building

A 20 × 30 ft building has a 100 ft perimeter, so it needs 100 linear feet of footing. At 16 in × 8 in, that is 100 × 0.89 = 88.9 ft³, or 3.29 yd³ of concrete: 149 × 80 lb bags exact, 163 bags to buy with waste.

That volume is well past the 1 yd³ crossover where a ready-mix truck usually beats bags — ready-mix suppliers bill a 1 yd³ minimum, which only makes bags cheaper on pours under a yard. At the example prices used on the main calculator ($6.50 per 80 lb bag, $160 per cubic yard, $75 delivery):

100 ft of 16 in × 8 in footingBags (with waste)Ready-mix truckWinner
3.29 yd³ (3.62 yd³ billed)163 bags = $1,059.503.62 yd³ billed = $654.42Ready-mix by ~$405

Labor settles it further. 163 bags at 80 lb is 13,040 lb of material to lift and mix, and a footing trench needs the whole run placed while the concrete is workable. A truck places the same footing in a single pass. Bags still make sense for short footing runs — a few fence or deck footings, a small shed, a repair — or where a truck simply cannot reach the trench. Run your own quotes through the cost comparison on the calculator before deciding.

Different Footing Size or Length?

Enter the trench in the free calculator as a rectangle: the footing width as one side, the total trench length as the other, and the footing depth as the thickness. It figures cubic yards, cubic feet, and bag counts live, and compares bag cost against a ready-mix quote with your local prices. Pouring a slab instead? See the bags per cubic yard guide or the 10×10 slab bag guide.

Open the Concrete Calculator →

Footing Concrete FAQ

How much concrete do I need per linear foot of footing?

It depends on the footing's cross-section. A 16 in × 8 in footing takes 0.89 ft³ per linear foot (about 15 × 80 lb bags per 10 ft, 17 with waste). A smaller 12 in × 6 in footing takes 0.50 ft³ per foot; a larger 24 in × 12 in takes 2.00 ft³ per foot.

How many bags of concrete for 100 feet of footing?

For the standard 16 in × 8 in footing: 149 bags of 80 lb mix exact, 163 to buy with the 10% waste allowance. That is 88.9 ft³, or 3.29 yd³ — a pour size where a ready-mix truck is usually cheaper and far less work.

How deep and wide does a footing need to be?

Width is driven by the load and your soil's bearing capacity; 16 in wide × 8 in deep is a common size under a one-story wall on average soil. Depth is driven by frost: the bottom of the footing must sit below your local frost line. Minimum sizes and reinforcement are set by local building code, so confirm the required dimensions with your building department or a licensed professional before digging.

Can I calculate a footing with the slab calculator?

Yes. A strip footing is just a long, narrow slab. Enter the footing width as the width, the total trench length as the length, and the footing depth as the thickness, and the calculator returns the same cubic yards and bag counts shown here, with a bag-vs-truck cost comparison.

Estimates Only

Results are planning estimates. Actual concrete needs vary with ground conditions, form accuracy, over-excavation, and product yield — trench footings in particular tend to run over the drawn dimensions. Bag yields follow manufacturer figures for standard mixes; your product may differ slightly. Always order a little extra — running short mid-pour creates a weak cold joint. For structural work (foundations, load-bearing footings, retaining walls), consult a licensed professional and follow your local building code.